How Long a Remodel Really Takes, and What Moves the Date

On this page

Timelines for custom remodels can vary widely depending on the needs of the home. However, project durations typically are: most bathrooms take six to eight weeks, most kitchens take eight to fourteen, and most additions take three to six months. Once a job is underway, weather, changes in homeowner requests or scope, material lead times, and conditions found behind walls and floors during demolition can move a finish date.

What You Need to Know

A remodel often takes longer than most homeowners expect because of the order the trades work in. Even a small bathroom needs every licensed trade in the building, and only one of them can be in the room at a time. That's why four weeks is a fast turnaround and six to eight is normal. The schedule you get before signing is dynamic, and you can see updates in real time in JobTread as well as get updates during check-ins with your Project Manager. Because we are fixed price contractors, a delay costs us rather than you, and our project managers are evaluated on their ability to finish on time or ahead of schedule.


A common nightmare scenario for homeowners is that the renovation runs twice as long as initially promised. A six-week project turns into four months after the crew disappears without explanation or communication.

When we hand you a finish date, you have every reason to question it and it is our job to justify it. Here's how we determine that date, what factors can move it, and how you can access updates in real time.

What's realistic, by project

These are ranges. Your project's own schedule comes with your estimate.

  • A bathroom with no plumbing relocated: four weeks on the quick end, six to eight more often
  • A kitchen: eight to ten weeks, twelve to fourteen if it's complex
  • A home addition: three to six months
  • A screened porch or deck: one to three months
  • Pre-construction, meaning signing to demo: one to six months

That last one surprises people most. Design gets finalized, permits get pulled, selections get made, and long-lead items get ordered before anyone swings a hammer. It's the least visible stretch of the project and it's the one that decides whether the rest of the schedule holds.

Why does a bathroom take six weeks?

We get this question any time we remodel a bathroom, and it is a great example of estimating a timeline. "A bathroom is a small room; how can the remodel take a month and a half?"

The primary reason is that a bathroom needs every single trade, and only one of them can work there at a time. The plumber, electrician, HVAC tech, drywaller, tile setter, trim carpenter, and painter all need the room to do the work right. Once tile goes down, nobody can walk on it for a while, so it sits empty on purpose.

Ten extra square feet of tile is not the difference between a six-week project and a two-week one. Small square footage saves you some on materials, but the labor costs stay about the same.

RJ Crai, our Project Development Manager, is blunt about shorter promises:

"If anyone's popping your bathroom out in two or three weeks, I'd have some questions."

RJ Crai, Project Development Manager

What can move your finish date

Four things account for most changes:

Unplanned custom requests: If your framing is up and three weeks later you want to bump out a closet, that's a change order. Design has to weigh in, trades have to get back on the calendar, and materials have to be ordered. One practical tip is worth remembering here: if a trade is scheduled to come out and you're thinking about adding scope, tell your Project Manager before they arrive. Planning ahead of time helps prevent delays.

Selections: Custom cabinetry can take several weeks to build and transport. Certain windows and appliances take longer to source. Lead times are the most common reason a schedule moves, which is why we push you toward the long-lead selections first instead of the hardware and accessories that feel easier to decide.

What's behind the wall: Older homes hide things. Termite damage, water rot, framing that was never right. When we find something, you'll hear what it is, how much time it adds, and why.

Weather: Exterior work shouldn't be completed in the rain, and an inch of ice in the South can shut everything down. We take quality and safety seriously and sometimes have to work around the weather.

You watch the schedule yourself

Your schedule lives in JobTread and you get access the day you sign. It's live. When something moves, it moves there, and you can see it without calling anyone. You also have regular meetings with your PM to go over the upcoming schedule and decisions that need to be made. The rest of what you can expect to hear from us, and when, is covered in who you'll hear from, and how often.

Who is accountable for your finish date?

"Our Project Managers are incentivized and analyzed based on getting the job done on time."

RJ Crai, Project Development Manager

That is a key part of how our PMs' performance is measured, which puts your finish date inside somebody's job description.

Because we are a fixed price contractor, job delay costs land on us. Seth Wilson, our Director of Operations, says it directly: "The longer we spend on a job, the less profitable it is for us. It does not affect your bottom dollar in the least." Nobody here has a reason to let your project drift. That's the same structure we walk through in why a remodel costs what it does, and how the number stays put.

The stretch where it feels stalled

Every project has one, and it's worth knowing about before you're in it.

Demo and rough-in are exciting! You can see the bones of the house and everything feels like progress. Then comes drywall. Insulation goes in, board goes up, gets taped, mudded, sanded, and prepped for paint. It takes a while in this stage and doesn't look like much is changing.

That's the point in almost every remodel where homeowners start wondering whether momentum has slowed down. The work is moving at the same pace it always was. Once paint, flooring, tile, and cabinets start going in, the whole thing comes together fast.

The standard experience

After working with us on several projects and properties over the years, one homeowner made it clear why he came back after the first job was completed:

"Met every deadline and didn't increase the price because they did a great job of estimating upfront costs."

K. C.

Delivering an experience where you get a great remodel that is on budget and on time is what we strive to do.

The bottom line

Remodeling timelines run long because of the trade schedule and the effort it takes to do exceptional work. Ask any contractor you consider to provide a written schedule before you sign, and ask how you'll see updates when something changes. A builder who can answer your questions has thought about your calendar. A builder who can't is asking you to take their best guess on faith.

Ask us on the first call

Ask how long your project should take. It's a fair question and you'll get a real answer.